We are almost to the finish line! The work remaining on the parsonage renovation is more or less a punch-list - just a few more items.
✅Appliances installed - just a few more wires to connect on some outlets and the kitchen sink disposal.
✅Lighting is installed and looks great!
✅Front storm door installed; the rear porch door is delivered and will go on after painting.
✅Back porch railings up; painting is happening today
✅All the plumbing finished
✅Grounded outlets were installed upstairs; the entry hall, stairs, and upstairs hall were painted (no more red!); the front guest bedroom was painted.
✅A few more this-n-that details, and the work will be finished!
It looks like a whole different house. I can't wait to get back to normalcy, although I will miss the steady stream of early morning friends helping me wake up each day to the sound of paint sprayers, hammers, and saws.! Here are some pictures of the progress.
Continued thanks to the Parsonage Committee for overseeing the work and answering the many little questions that come up from time to time, and to Brad and Tony Wesley, and to Jamie, Jason, Francisco, Gustavo, and all the folks that have made this such a smooth and beautiful project. Thanks too to all the generous folks from Long Memorial who have supported this project for the benefit of future pastoral families and me!
Blessings,
Pastor Ed